Structure | Reinforced Concrete |
---|---|
Wall | Cement Sand Brick/ Clay Brick (Party Wall) |
Roof Covering | Main Roof- Concrete Roof Tiles, Car Porch - Metal Deck |
Roof Framing | Light Weight Steel Trusses |
Ceiling | Plaster Ceiling / Skim Coat |
Ironmongery | Provided |
---|---|
Internal Telecommunication & Cabling | Provided |
Fencing | Provided |
Turfing | Not Provided |
Aluminium Frame Casement |
---|
Aluminium Frame Top Hung |
Aluminium Frame Fixed Glass |
Main Entrance | - Timber Door |
---|---|
Other Doors | - Timber Door - Aluminium Frame Glass Sliding Door - Aluminium Frame Folding Door |
Bathroom | - Tiles up to Ceiling Height |
---|---|
Kitchens | - Tiles up to 1500mm High / Plaster & Paint |
Others | - Plaster & Paint |
Driveway | - Concrete Imprint |
---|---|
Yard | - Tiles |
Lobby, Living, Dining & Kitchen | - Tiles |
Bedroom 5 | - Tiles |
Home Office | - Tiles |
Utility | - Tiles |
Linen | - Cement Render |
Master Bath, Bath 2,3,4 & 5 | - Tiles |
Refuse Compartment | - Tiles |
Family Lounge & Hallway | - Laminated Flooring |
Master Bedroom, Bedroom 2,3 & 4 | - Laminated Flooring |
Staircase | - Laminated Flooring |
Balcony | - Tiles |
SANITARY AND PLUMBING FITTINGS | TYPE | ||||||||
A | A (MIRROR) | ||||||||
: Kitchen | Sink with Tap | 1 | 1 | ||||||
: Bathrooms | Water Closet | 5 | 5 | ||||||
Wash Basin with Tap | 5 | 5 | |||||||
Shower Rose | 5 | 5 | |||||||
Hand Bidet | 5 | 5 | |||||||
Paper Roll Holder | 5 | 5 | |||||||
: Yard | Bib Tap | 1 | 1 |
ELECTRICAL INSTALLATION | TYPE | |||||||
A | A (MIRROR) | |||||||
: Lighting Point | 42 | 42 | ||||||
: Power Point | 30 | 30 | ||||||
: Fan Point | 8 | 8 | ||||||
: TV Point | 3 | 3 | ||||||
: Telephone Point | 1 | 1 | ||||||
: Auto Gate Point | 1 | 1 | ||||||
: Door Bell Point | 1 | 1 | ||||||
: Air Conditioner Point | 7 | 7 | ||||||
: Water Heater Point | 4 | 4 | ||||||
: Booster Pump Point | Provided | Provided |
Developer Name: Setia Bayuemas, Klang • Phase: Phase A19B Double Storey Semi-Detached • Company Name: I&P Kota Bayuemas Sdn. Bhd. (200201000854) (a member of Setia) • Developer Address: Bandar Kinrara Welcome Centre, Eight Kinrara – Block B, Jalan BK 5A/1, Bandar Kinrara, 47180 Puchong, Selangor Darul Ehsan Tel: 03-80829600 • Email: bayuemas@spsetia.com • Developer’s License No: 9796/01-2029/1432(A) • Validity Period: 07/01/2024 - 06/01/2029 • Advertising and Sales Permit No: 9796-24/11-2026/1042(N)-(L) • Validity Period: 13/11/2024 - 12/11/2026 • Approving Authority: Majlis Perbandaran Klang • Building Plan Approval No: (8) DLM MPK/BGN-600-5/1/0111(2023) • Expected Date of Completion: November 2026 • Land of encumbrance: Nil • Tenure of Land: Freehold • Restrictions in Interest: Nil • Number of Units:
Site Plan
Location

Location
Located in one of Klang’s most sought-after locations, Ambrosia II is articulately built to ensure an organised neighbourhood that offers optimum security, conveniences and a clean and clutter-free environment.
Sekolah Jenis Kebangsaan Cina Wu Teck |
Sekolah Kebangsaan Kampung Johan Setia |
Sekolah Kebangsaan Kampung Pendamar |
Aeon Bukit Tinggi |
Tesco Bukit Tinggi |
GM Klang |
Giant Hypermarket Bukit Tinggi |
KSL Esplanade Shopping Mall |
Poliklinik Cahaya (Pandamaran) |
Klinik Kesihatan Bandar Botanik |
Klinik Mediviron Bandar Parklands |
Lebuhraya Shah Alam (KESAS) |
Lebuhraya Kemuning-Shah Alam (LKSA) |
ELITE Expressway |
Gallery



Ambrosia II as at 8/1/2025 - The foundation of the said building are in progress.
Ambrosia II as at 7/3/2025 - The foundation of the said building are in progress.
Ambrosia II as at 5/5/2025 - The foundation of the said building are in progress.